Sunday, March 04, 2007

Foundation Forms Installed and Concrete Walls Poured


The foundation walls are here! They are installed and now we are ready to pour the concrete walls.












We've got it going on today. We are pouring the concrete walls and bring in back fill to fill in around the foundation once the walls are complete. This was one of the high lights of the day... two dump trucks and a concrete truck sandwiched in between.

The concrete trucks and the concrete pump have arrived. The truck pours it into the pump and the pump elevates it up the boom and back down to be poured.


The forms are filled with concrete. The workers did a great job. We are so blessed with such hard worker!


The concret is dry and the forms are removed. The forms were removed the next day. Hannah and Danile climb on the stock pile. The dirt will be piled against the walls when the walls have set more.